At Lilac Station, we prioritize the well-being and relaxation of our residents with an array of self-care amenities. Step into our state-of-the-art fitness center, where you can engage in invigorating workouts tailored to your fitness goals with our interactive workout mirror. On the second floor lies our tranquil yoga studio, offering a serene space for…
Lilac Station Blog
Lilac Station's construction is steadily progressing into the spring season. We have a lot of news to share with you as we get closer to move-in! Let's spring into those updates! Unit electric testing and punching are complete on all floors, and furnaces are operational in all units. On top of that, the wireless service…
We're only a few months away from opening, and time is flying by! So much work is being completed here at Lilac Station, and we can't wait to share our latest developments with you. This time, we have a lot of things finished – woot, woot! The lighting installation on the amenity deck, conference room,…
It's 2023 – the year we're opening! We are thrilled to open this year and hope that you – yes, you – will apply to live with us. We aren't open just yet, but we can keep you up to date on our progress. Many of our updates come from the fourth floor, meaning that…
On the 5th day of construction, Lilac Station gave to me…"five carpet installs"! Although we are still installing carpet throughout Lilac Station, we are progressing quickly and can't wait to open in 2023! So consider this holiday update to be our gift to you. We'll start with the basics. Topsoil installation around Lilac Station is…
This Thanksgiving we are thankful for the quick construction progression on Lilac Station! The progress at our new building is moving along nicely! We're excited to share with you what we've been up to in recent weeks. On the 1st floor, unit corridor painting and countertop installs with sinks are complete while plumbing finishes are…
Now that it's spooky season, we are carving out some spooky construction at Lilac Station. Drop ceilings have been installed in the lobby and on the 2nd floor, and they are actively being installed on the 3rd floor. Drywall is continuing in the 1st floor common area rooms, and insulation on the north side of…
Since August, we have been continuously moving on up with our construction progress, and we can’t wait to show you the finished product! Fortunately, we can update you on our current construction progress! Plumbing, electrical, and mechanical installation are still ongoing, but they have been moving up to floors two and three. Masonry has finished…
To say we are thrilled is an understatement! Lilac Station construction progress is in full swing and we are here for it! Electrical, plumbing, and mechanical are in the works throughout the building. Masonry work is still in progress but taking shape. Lilac Station is taking shape and we couldn't be happier!
We've been hard at work these past few weeks, and we can't wait to show you what it's going to look like when it's finished. For now, we are happy to report that framing, walls, and windows are installed. Even some masonry has been completed. You can see it coming to life! While there is…